Mozambique LNG
TotalEnergies-operated 13.1 mtpa onshore LNG project at Afungi, Cabo Delgado. Force majeure (declared 2021 after the Palma attack) was lifted November 7, 2025; construction restarted with first LNG targeted for 2029.
Record verified against census 2026-11: OGJ 2026-01-29; World Oil 2025-10-24; S&P Global 2021-04-26. Tracked since 2026-10.
From the public record
- 2021-04-26
Force majeure declared and staff withdrawn from Afungi. TotalEnergies declared force majeure and removed all staff from the site after the militant offensive on Palma in late March 2021.
- 2025-11-07
Consortium lifts force majeure. The consortium had informed Mozambique's presidency on October 24, 2025; its later statements date the decision to lift to November 7, 2025.
- 2026-01
Full restart of onshore and offshore construction. The project reported construction restarted at Afungi with progress at about 40% and first LNG expected in 2029.